Burlington School District (BSD) is issuing a Request for Proposals (RFP) for an architect-led design team to provide architectural and engineering services for development of a new Burlington High School and Technical Center. The full Request for Proposals document is available upon request via the means provided below.
Project Description:
Based on previous programming and design work, the size of the new high school and technical center is expected to be in the range of 250,000 – 300,000 square feet. The new building will include all program space required by Burlington High School, Burlington Technical Center, ONTOP and Horizons.
Scope of Work:
The Scope of Services shall include all design and analysis services to permit and construct the project including but not limited to architectural design, mechanical, electrical, and plumbing (MEP) design, structural engineering, civil engineering (including geotechnical and stormwater design), traffic/transportation engineering, and landscape and lighting design.
Project Location: 52 Institute Road, Burlington VT
Target Schedule:
Pre-Bond Drawings and Cost Estimate – August 2022
Bond Vote Date –November 2022.
Occupancy Date – August 2025
Submission information: Requests to obtain the full RFP must be made no later than November 10, 2021 (10:00 AM) to Burlington School District Director of Property Services, Marty Spaulding at mspauldi@bsdvt.org or 802-864-8453. A mandatory site visit will be held November 10, 2021 (1:00 PM). Proposals will be due by November 26, 2021 (3:00 PM).